Here are the latest updates on two Harris County Precinct 4 projects for Mueschke Road on the west side of Tomball.

Ongoing projects

Mueschke Road widening south of Draper Road

Project: Mueschke Road is being widened from two to four lanes from Amira Drive to Draper Road, with the project meant to bring drainage improvements to the roads.

Update: The project is expected to finish construction this fall, according to an update from the infrastructure division of Harris County Precinct 4.

  • Timeline: set to be complete this fall
  • Cost: $7.75 million
  • Funding source: Harris County Precinct 4 mobility funds

Upcoming projects



Mueschke Road widening south of FM 2920

Project: Mueschke Road will be widened from two lanes to four lanes between Draper Road and FM 2920.

Update: This project is being designed, with construction expected toward the end of 2025, according to Harris County Precinct 4.

  • Timeline: late 2025-TBD
  • Cost: $8 million
  • Funding source: TBD