Here are the latest updates on two Harris County Precinct 4 projects for Mueschke Road on the west side of Tomball.
Ongoing projects
Mueschke Road widening south of Draper Road
Project: Mueschke Road is being widened from two to four lanes from Amira Drive to Draper Road, with the project meant to bring drainage improvements to the roads.
Update: The project is expected to finish construction this fall, according to an update from the infrastructure division of Harris County Precinct 4.
- Timeline: set to be complete this fall
- Cost: $7.75 million
- Funding source: Harris County Precinct 4 mobility funds
Upcoming projects
Mueschke Road widening south of FM 2920
Project: Mueschke Road will be widened from two lanes to four lanes between Draper Road and FM 2920.
Update: This project is being designed, with construction expected toward the end of 2025, according to Harris County Precinct 4.
- Timeline: late 2025-TBD
- Cost: $8 million
- Funding source: TBD