Several road projects are planned or underway in the Cy-Fair area. This list is not comprehensive.

UPCOMING PROJECTS

1. Cypress North Houston Road traffic signal

Project: A new mast arm traffic signal is being installed on Cypress North Houston Road at Barker Trace.

Update: This project is in the design phase.
  • Timeline: Estimated start and completion in the second quarter of 2024
  • Cost: $500,000
  • Funding source: Harris County Precinct 3
2. Cumberland Ridge Drive traffic signal


Project: A new mast arm traffic signal is being installed on Cumberland Ridge Drive at Fairfield Place.

Update: This project is in the design phase.
  • Timeline: Estimated start and completion in the third quarter of 2024
  • Cost: $500,000
  • Funding source: Harris County Precinct 3
3. Cypress North Houston Road widening

Project: Cypress North Houston Road is being widened from Perry Road to Jones Road. The project also includes new or upgraded traffic signals at Autumn Mills Road, Misty Moss Lane and Jones Road.

Update: This project is in the design phase.
  • Timeline: TBD
  • Cost: $7.5 million
  • Funding source: Harris County Precinct 3
4. Mason Road, Cypresswood Drive intersection improvements


Project: Dual left-turn lanes on the southbound approach and traffic signal modifications are planned.

Update: This project is in the design phase.
  • Timeline: First quarter of 2024-second quarter of 2024
  • Cost: $415,000
  • Funding source: Harris County Precinct 3
5. Mound Road extension

Project: Mound Road will be extended from Greenhouse Road to the Hot Wells shooting range.

Update: This project is in the design phase.
  • Timeline: Third quarter of 2024-fourth quarter of 2024
  • Cost: $1.5 million
  • Funding source: Harris County Precinct 3
6. Telge Road reconstruction


Project: Telge Road will be reconstructed from Wyman Gordon Way to Hwy. 290, including the addition of new roadway signage.

Update: This project is in the design phase.
  • Timeline: TBD
  • Cost: $2 million
  • Funding source: Harris County Precinct 3
7. West Road traffic signal

Project: A new mast arm traffic signal is being installed on West Road at Bridge Park Drive.

Update: This project is in the design phase.
  • Timeline: Third quarter of 2024-fourth quarter of 2024
  • Cost: $500,000
  • Funding source: Harris County Precinct 3
ONGOING PROJECTS


8. Greenhouse Road bridge


Project: A bridge along Greenhouse Road is being built over Cypress Creek.

Update: Construction begins in the first quarter of 2024.
  • Timeline: First quarter of 2024-second quarter of 2025
  • Cost: $8.7 million
  • Funding source: Harris County Precinct 3
9. Schiel Road widening

Project: Schiel Road is being widened from a two-lane asphalt roadway to a four-lane concrete boulevard with a raised median and underground storm sewer.


Update: Construction is underway.
  • Timeline: Estimated completion in the second quarter of 2024
  • Cost: $5.4 million
  • Funding source: Harris County Precinct 3