Construction is underway on converting Schiel Road from a two-lane asphalt road to a four-lane concrete boulevard with a raised median and underground storm sewer. The project is taking place in two phases: Segment 1 is from east of the Grand Parkway to west of Fairfield Place Drive, and Segment 2 is from west of Fairfield Place Drive to west of Mason Road for a total cost of $9 million, according to Harris County Precinct 3 officials.

Timeline: construction complete in second quarter 2023 (Segment 1), third quarter 2023 (Segment 2)

Cost: $4.8 million (Segment 1), $4.2 million (Segment 2)

Funding source: Harris County Precinct 3