1. Exhibit Center renovations: A nearly 9,000-square-foot addition will bring the facility’s capacity from 600 to 1,593, including stadium-style and floor seating. The expansion also includes more restrooms and meeting space.
Estimated completion: April
Cost: $8.98 million
2. Brautigam Center addition: A career and technical education expansion project is underway at the Brautigam Center. The 12,000-square-foot addition will include labs and shop spaces. This campus serves students ages 16-21 who are catching up on graduation credits or working to graduate in less than four years.
Estimated completion: July
Cost: $6.64 million
3. Elementary School No. 57: A new two-story elementary school is under construction on a 16.7-acre tract in the Bridgeland area. The campus will feed into Smith Middle School and Bridgeland High School.
Estimated completion: August
Cost: $32.6 million
4. Transportation Center No. 6: Cy-Fair ISD’s sixth transportation center is under construction next to Cypress Woods High School. The project includes a new facility with administrative space, vehicle service space, mechanical and support spaces, covered bus parking, a bus fueling station and a two-story training center.
Estimated completion: December
Cost: $28.48 million
5. Visual & Performing Arts Center: An 85,000-square-foot facility will serve the district with a 1,500-seat auditorium, a small secondary theater, a dance studio and fine arts support spaces.
Estimated completion: December
Cost: $51.14 million
Mark Henry, Ed.D. Administration Building: Located on the same property as the new Visual & Performing Arts Center, the 220,000-square-foot project features a five-story office tower for district employees as well as a 250-seat board room, a conference center and a video production studio on the first floor.
Estimated completion: November
Cost: $58.79 million