Ongoing projects
1. Hwy. 105 widening
Project: Hwy. 105 is being reconstructed and widened from two to four lanes from 10th Street to South Loop 336.
Update: According to a Nov. 1 media update from the Texas Department of Transportation, this project is 34% completed.
- Timeline: March 2023-third quarter 2027
- Cost: $52.35 million
- Funding source: state funds
Project: Between FM 830 and FM 1097 in Willis, I-45 is undergoing a northbound ramp reversal.
Update: This project is 50% complete, according to a Nov. 1 media update from TxDOT.
- Timeline: February 2024-second quarter 2025
- Cost: $3.17 million
- Funding source: state funds
Project: Between South Loop 336 to FM 1484, Hwy. 105 is being widened and reconstructed from two to four lanes.
Update: According to a Nov. 1 media update from TxDOT, this project is 79% complete.
- Timeline: February 2023-third quarter 2026
- Cost: $89.71 million
- Funding source: state funds
Project: TxDOT is using an existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections.
Update: This project is 37% complete, according to a Nov. 1 media update from TxDOT.
- Timeline: October 2023-first quarter 2026
- Cost: $29.11 million
- Funding sources: federal, state funds
5. Eastbound flyover construction on Hwy. 242
Project: Montgomery County commissioners and TxDOT are funding the construction of a flyover from northbound I-45 to eastbound Hwy. 242.
Update: According to the TxDOT project tracker, the project was given notice to proceed on Oct. 2 and an estimated completion date was given for Sept. 15, 2026. A date to begin work was not specified.
- Timeline: late 2024-September 2026
- Cost: $19.1 million
- Funding sources: Montgomery County, federal funds