Here are the latest updates on four transportation projects happening around the Conroe and Montgomery area.

Hwy. 105 widening

Project: Hwy. 105 between 10th Street and South Loop 336 is being reconstructed and widened from two to four lanes.

Update: This project is 24% complete, according to a May media update from the Texas Department of Transportation.

  • Timeline: March 2023-third quarter 2027
  • Cost: $51.83 million
  • Funding source: state funds

FM 1486 repairs

Project: FM 1486 is undergoing overlay and base repairs between Hwy. 105 and FM 1774.



Update: This project is 94% complete, according to a May media update from TxDOT.

  • Timeline: October 2023-third quarter 2024
  • Cost: $4.57 million
  • Funding source: state funds

Hwy. 105 reconstruction

Project: Between South Loop 336 and FM 1484, Hwy. 105 is being reconstructed and widened from two to four lanes.

Update: According to a May media update from TxDOT, this project is 52% complete.

  • Timeline: October 2022-third quarter 2027
  • Cost: $89.88 million
  • Funding source: federal, state funds

FM 1097 widening

Project: From Lake Conroe Hills Drive to Blueberry Hill Road, FM 1097 is being widened from two to four lanes with a continuous left-turn lane.



Update: This project is 45% complete, according to a May media update from TxDOT. The project also has a delay due to bridge redesign.

  • Timeline: second quarter 2022-first quarter 2025
  • Cost: $20.20 million
  • Funding source: federal, state funds