Here are the latest updates on four transportation projects happening around the Conroe and Montgomery area.
Hwy. 105 widening
Project: Hwy. 105 between 10th Street and South Loop 336 is being reconstructed and widened from two to four lanes.
Update: This project is 24% complete, according to a May media update from the Texas Department of Transportation.
- Timeline: March 2023-third quarter 2027
- Cost: $51.83 million
- Funding source: state funds
FM 1486 repairs
Project: FM 1486 is undergoing overlay and base repairs between Hwy. 105 and FM 1774.
Update: This project is 94% complete, according to a May media update from TxDOT.
- Timeline: October 2023-third quarter 2024
- Cost: $4.57 million
- Funding source: state funds
Hwy. 105 reconstruction
Project: Between South Loop 336 and FM 1484, Hwy. 105 is being reconstructed and widened from two to four lanes.
Update: According to a May media update from TxDOT, this project is 52% complete.
- Timeline: October 2022-third quarter 2027
- Cost: $89.88 million
- Funding source: federal, state funds
FM 1097 widening
Project: From Lake Conroe Hills Drive to Blueberry Hill Road, FM 1097 is being widened from two to four lanes with a continuous left-turn lane.
Update: This project is 45% complete, according to a May media update from TxDOT. The project also has a delay due to bridge redesign.
- Timeline: second quarter 2022-first quarter 2025
- Cost: $20.20 million
- Funding source: federal, state funds