1. Hwy. 105 reconstruction
Project: The project will reconstruct and widen Hwy. 105 from two to four lanes between 10th Street in Conroe and South Loop 336.
Update: The Texas Department of Transportation reported the project is 8% completed as of an Oct. 1 update, the latest available.
- Timeline: March 2023-third quarter 2027
- Cost: $51.83 million
- Funding source: TxDOT
Project: The project will reconstruct and widen Hwy. 105 from two to four lanes between South Loop 336 in Conroe to FM 1484.
Update: TxDOT reported the project is 27% completed as of an Oct. 1 update, the latest available.
- Timeline: February 2023-third quarter 2026
- Cost: $89.72 million
- Funding source: TxDOT
Project: The project builds a new three-lane northbound frontage road between FM 830 and FM 1097 in Willis along I-45.
Update: TxDOT reported the project is wrapping up and was 96% completed as of an Oct. 1 update, the latest available.
- Timeline: September 2022-tentative fourth quarter 2023
- Cost: $7.48 million
- Funding sources: TxDOT, federal
Project: The project will add a raised median along FM 1488 between Mostyn Drive in Magnolia and I-45 in Conroe.
Update: TxDOT reported the project is underway and 15% completed as of an Oct. 1 update, the latest available.
- Timeline: summer 2023-tentative fourth quarter 2025
- Cost: $10.22 million
- Funding sources: TxDOT, federal
Project: The project will widen FM 1097 in Willis from two to four lanes with a continuous left turn lane between Lake Conroe Hills Drive and Blueberry Hills Road.
Update: TxDOT reported the project is 30% completed as of an Oct. 1 update, the latest available.
- Timeline: second quarter 2022-first quarter 2024
- Cost: $16.09 million
- Funding sources: TxDOT, federal
Project: The project includes overlaying FM 2854 and adding turn lanes between Hwy. 105 and the San Jacinto River.
Update: TxDOT reported the project is 62% completed as of an Oct. 1 update, the latest available.
- Timeline: January 2023-first quarter 2024
- Cost: $10.41 million
- Funding sources: TxDOT, federal
Project: The project will include overlay and base repair work on FM 1486 from Hwy. 105 to FM 1774 in the Montgomery area.
Update: The project is tentatively slated to begin in October.
- Timeline: TBD
- Cost: $4.57 million
- Funding source: TxDOT