Hwy. 105 improvements
TxDOT is adding a raised median, widening the pavement and modifying traffic signals on Hwy. 105 between FM 2854 and I-45 from Montgomery to Conroe. The project was 90% completed as of a July 6 update, the latest available, from TxDOT. It’s slated to finish in the first quarter of 2024.
- Timeline: October 2021-first quarter 2024
- Cost: $9.83 million
- Funding sources: federal, state
A three-lane northbound frontage road is under construction along I-45 between FM 830 and FM 1097 in the Willis area. The project is slated to wrap up by year’s end and was 76% completed as of a July 6 update.
- Timeline: September 2022-fourth quarter 2023
- Cost: $7.47 million
- Funding sources: federal, state