The Texas Department of Transportation is continuing its work to improve Hwy. 105 between FM 2854 and I-45 from Montgomery through Conroe. Raised median barriers are being constructed, and the project also includes widening the pavement and modifying traffic signals. The project was 23% completed as of June 1, the latest available update from TxDOT.

Timeline: October 2021-third quarter 2023

Cost: $9.83 million

Funding sources: federal, state