1. Janet K. Bartlett Elementary School
Project: The new school, funded by the 2019 bond package, will serve up to 950 students in pre-K through fourth grades in the Caney Creek and Conroe high school feeder zones.
Update: Construction is complete and the school is on track to welcome its first students in August, Easy Foster, director of planning and construction at Conroe ISD, said July 16.
Location: 11225 Cielo Drive, Conroe
Timeline: 2019-August
2. Rob Eissler Elementary School
Project: The new elementary school, funded by the 2023 bond, will have a 950-student capacity and serve the The Woodlands High School feeder zone.
Update: Construction is on schedule and retention ponds have been built to control water on-site, district officials said July 16.
Location: 14000 Old Conroe Road, Conroe
Timeline: March 2024-August 2025
3. Mittie J. Campbell Elementary School
Project: The new elementary school will have a 950-student capacity in the Oak Ridge and Caney Creek high school feeder zones.
Update: Construction is ahead of schedule with driveways laid as of mid-July, district officials said July 16.
Location: 15895 Stonecrest Drive, Conroe
Timeline: March 2024-August 2025
4. Grand Oaks campus
Project: The new school will serve seventh, eighth and ninth grades in the Grand Oaks High School feeder zone.
Update: The crew is halfway through building pad construction and building new roads into the school, district officials said July 16.
Location: 28075 Woodson’s Grand Drive, Spring
Timeline: March 2024-January 2027
5. David Elementary School
Project: The school is performing roof, heating, ventilation and air conditioning renovations.
Update: The project is delayed by Hurricane Beryl.
Location: 5301 Shadowbend Place, The Woodlands
Timeline: Completion before the start of the 2024-25 school year
6. Lamar Elementary School
Project: The school is performing kitchen, roof, heating, ventilation and air conditioning renovations.
Update: This project is delayed by Hurricane Beryl, but it will not affect the district’s ability to serve students food on the first day of school, district officials said July 16.
Location: 1300 Many Pines Road, The Woodlands
Timeline: Completion before the start of the 2024-25 school year
7. Houser Elementary School
Project: The school is performing fire sprinkler, heating, ventilation and air conditioning renovations.
Update: The project is delayed due to Hurricane Beryl, district officials said July 16.
Location: 27370 Oak Ridge School Road, Conroe
Timeline: Completion before the start of the 2024-25 school year
8. Rice Elementary School
Project: The school is receiving heating, ventilation and air conditioning renovations.
Update: The project is delayed due to Hurricane Beryl, district officials said July 16.
Location: 904 Gladstell St., Conroe
Timeline: Completion before the start of the 2024-25 school year
9. Conroe High School
Project: The school is making improvements to its campus to accommodate student growth.
Update: The project is currently in the fine arts and dining phase of renovation.
Location: 3200 W. Davis St., Conroe
Timeline: Completion in December 2025