The following information may be subject to change.
1. Lupe Tortilla: 20269 Eva St., Montgomery
Type of work: renovation/alteration
Timeline: Feb. 13-Nov. 30
Estimated cost: $2 million
2. V Bistro: 4589 W. Davis St., Ste. 200, Conroe
Type of work: new construction
Timeline: Feb. 20-June 20
Estimated cost: $385,580
3. Giesinger Elementary School: 2323 White Oak Blvd., Conroe
Type of work: renovation/alteration
Timeline: May 25-July 25
Estimated cost: $4.8 million
4. Mister Car Wash: 21938 Market Place Drive, Montgomery
Type of work: new construction
Timeline: April 11-Dec. 13
Estimated cost: $1.6 million
5. First Montgomery Baptist Church: 20423 Eva St., Montgomery
Type of work: renovation/alteration
Timeline: March 1-Dec. 31
Estimated cost: $200,000