The gist
Seabrook city staff said July 2 they expected the work between Red Bluff Road and FM 96 was estimated to take two months to complete. However, Danny Perez, public information officer for TxDOT, said Aug. 2 the agency will be working “most likely through December.”
At that same July meeting, Seabrook City Manager Gayle Cook briefed Seabrook City Council on the status of a few TxDOT projects attached to Hwy. 146 and shared that TxDOT officials told her it was behind schedule.
“It has been a little quiet; I did check in with our TxDOT representative, and ... they said that they are probably still a couple of months out from probably pulling all the equipment, so they’re a little behind,” Cook said.
The details
The remaining improvements on the frontage roads adjacent to Hwy. 146 from Red Bluff Road to FM 96 include:
- Installing pavers, sod and sidewalks
- Driveway adjustments
- Completion of detention ponds
- Additional lane construction for southbound and northbound roads over the Red Bluff Road intersection
- Building a retention wall in late 2024 near the Red Bluff Road intersection