Grissom Road widening
Contractors have begun a project to widen Grissom Road in League City between Abigail Lane and West NASA Road from two to four lanes. The westbound lanes will be built first, followed by the eastbound lanes. As part of the project, street drainage will be improved, and contractors will install a new 12-inch water line from the city’s north booster station to West NASA Road.
Timeline: April 2022-April 2023
Cost: $8.53 million
Funding source: city of League City
Upcoming projects
Hobbs Road extension to FM 517
Hobbs Road will be extended to the south to connect with FM 517. The new road will be about 1,880 feet long and four lanes wide, though League City will construct only the two southbound lanes.
Timeline: fall 2023-TBD
Cost: $3.93 million
Funding source: city of League City