The details
The closure comes after League City City Council’s decision to award a $2.35 million contract to Houston-based B&D Contractor for the upgrades at its Sept. 23 meeting.
The details
The project will be divided into two phases.
Phase I
- Addition of six pickleball courts
- Baseball field upgrades
- Pedestrian bridge repairs
- Drainage improvements
- New security lighting installation
- 1,800-square-foot picnic pavilion
- Fitness course
- Multipurpose athletic fields
- Hiking trail
- Additional restrooms
- Additional parking
The park will reopen at the end of Phase I, which is scheduled to be completed in spring 2026, and will remain open for the project’s second phase.