7 transportation updates for Cedar Park-Leander for October 2019

East Street construction

East Street construction



Ongoing Projects


1. Metro Drive extension
Construction on a project extending Metro Drive from the Capital Metro Leander Station to Mel Mathis Boulevard began in July. Construction is expected to last until the end of May, according to Leander city spokesperson Mike Neu.
Timeline: July-May
Cost: $3.8 million
Funding source: Leander general obligation bonds








2. RM 2243 repaving
A project on RM 2243 repaves the road from US 13 to Weir Ranch Road. The project is mostly complete and just in need of final striping, according to Texas Department of Transportation spokesperson Brad Wheelis. The project is expected to be complete in October, according to Wheelis.
Timeline: August-October
Cost: $1.31 million
Funding source: TxDOT





Recent Updates


3. Brushy Creek Regional Trail connection
The city of Cedar Park has been in the process of adding missing parts of the Brushy Creek Regional Trail System. This project is taking place at  A Brushy Creek Lake Park, B Twin Lakes Park and C Little Elm Trail. The project is expected to be complete by late October, according to city spokesperson Jennie Huerta. While most of the sections are open to the public, the final section of Little Elm Trail west of Bell Boulevard should be open by mid-October while remaining cleanup takes place, according to Huerta.
Timeline: January-October
Cost: $285,000 (construction only)
Funding source: Cedar Park Community Development Corp. (Type B Board)








4. Bicycle Lane Phase 1A
Bicycle lanes are being expanded on four Cedar Park roads. The Bicycle Lane Phase 1A project adds 47,000 feet of bicycle lanes to existing pavement on  A Brushy Creek Road, B Little Elm Trail,  C New Hope Drive and  D Buttercup Creek Boulevard. Design of the bike lanes is complete, according to Huerta. The city is now evaluating contractor proposals.
Timeline: fall 2019
Cost: $350,000
Funding source: Cedar Park Community Development Co. (Type B Board)






Upcoming Projects


5. East Street construction
The project constructs a two-lane road from RM 2243 to Hero Way, with parallel parking on both sides of the street. The city plans to seek bids on the project in early 2020. The project should take 15 months to construct, according to Neu.
Timeline: TBD
Cost: $3,223,617
Funding source: city of Leander






6. Raider Way and East Woodview Drive improvements
The city of Leander has plans for a project aimed to improve traffic flow around Wiley Middle School and Rouse High School. The project includes widening Raider Way from East Woodview Drive to East Crystal Falls Parkway and East Woodview from Toll 183A to Raider to four lanes. The city is in the process of acquiring rights of way, and construction is expected to start early 2020.
Timeline: TBD
Cost $7.86 million
Funding source: Leander general obligation bonds








7. Crystal Falls Parkway sidewalks
The city of Leander is preparing to complete sidewalk gaps along Crystal Falls Parkway between Glass and Overland drives. Leander City Council voted in January to have engineering firm Binkley & Barfield design, bid and provide construction administration services on the project. Plans for the project are still under review by the city.
Timeline: TBD
Cost: $274,000
Funding source: Leander general fund


SHARE THIS STORY


MOST RECENT

(Brian Perdue/Community Impact Newspaper)
Fifteen Leander ISD employees to receive advanced degrees from Concordia University Texas

Fifteen Leander ISD employees will receive advanced degrees from Concordia University Texas during the Dec. 7 commencement.

Kent Cagle was Leander's city manager from 2011 until May of this year. (Courtesy city of Leander)
Former Leander City Manager Kent Cagle now city manager of Killeen

Cagle’s first day as city manager of Killeen was Dec. 3, according to a city press release.

Travis County commissioners received their sixth update on the 2017-22 bond program at a Dec. 3 meeting. (Emma Freer/Community Impact Newspaper)
Travis County 2017-22 bond program remains on track thanks to innovations

Fifty-six of the 60 projects included in the five-year bond program Travis County voters approved in 2017 are in active development, according to a Dec. 3 presentation made to the Commissioners Court.

Juanita Budd began work as the new general manager of Brushy Creek MUD on Dec. 1.
Brushy Creek MUD selects new general manager

Juanita Budd began as the new general manager of the Brushy Creek Municipal Utility District, or MUD, on Dec. 1.

The Williamson County seat is located in Georgetown at 710 S. Main St. (Ali Linan/Community Impact Newspaper)
Williamson County sees one of the largest year-over-year employment increases in the U.S.

Williamson County continues to see its unemployment rate decline.

The Leander ISD draft 2020-21 school calendar (pictured) is also available online at www.leanderisd.org. Trustees are scheduled to discuss, and possible vote on, the calendar at the Dec. 12 meeting. (Courtesy Leander ISD)
Leander ISD to discuss proposed 2020-21 school calendar

Leander ISD has published its draft calendar for the 2020-21 school year

(Brian Perdue, Community Impact Newspaper)
Two LISD employees to receive doctorate degrees

Jim Rose and Sarah Martinez will be part of the first class ever to receive doctorate degrees conferred by Concordia University Texas.

Williamson County commissioners approved a grant application for a mental health jail diversion program at a Nov. 26 meeting.
Williamson County commissioners approve grant application for mental health jail diversion program

Williamson County commissioners unanimously approved an application for more than $1 million in grant funding that would support mental health services in the local criminal justice system.

Jeff Williams stands outside his future shop location. (Courtesy Jeff Williams)
Motorcycle shop moving from Lake Travis to Cedar Park

Sinners Cycle Shop, currently at 4601 Hudson Bend Road, Ste. 100, Austin, plans to move to 1300 W. Whitestone Blvd., Bldg. F (formerly Hutch’s Auto Body Shop), Cedar Park

The Travis County Juvenile Public Defender's Office currently represents around 70% of juvenile defendants. Sources: Texas Indigent Defense Commission, Travis County Juvenile Public Defender’s Office/Community Impact Newspaper
New Travis County Public Defender's Office aims for better legal outcomes

A majority of adult defendants could qualify for the new office, which is set to open in 2021.

Taps line the bar at Austin Beerworks in North Austin.
These Austin-area breweries are celebrating Small Business Saturday

More than a dozen Austin-area breweries and restaurants are celebrating Small Business Saturday this year by selling limited-edition glassware to participating customers.

(Courtesy Thundercloud Subs Turkey Trot)
7 Austin-area turkey trots to get you feeling extra thankful this holiday season

Winner, winner, turkey dinner: Check out these seven Austin-area turkey trots happening this Thanksgiving.

Back to top