Update: The project paused in November, and new intersection design options were brought to Southlake council, but no changes were made to the construction plan. The work resumed Jan. 5.
- Timeline: To be completed this summer
- Cost: $1.05 million
- Funding source: city of Southlake, TxDOT
4. Bransford Road sidewalk constructionProject: The project includes building an 18,000-square-foot sidewalk to connect Colleyville City Park to Shelton Drive. Storm drainage improvements will occur.
Update: The project was delayed due to winter weather and has roughly 85% of the storm drain installed and 90% of the sidewalk installed, Assistant City Manager Adrienne Lothery said.
- Timeline: substantial completion mid-late February
- Cost: $991,222
- Funding source: city of Colleyville
5. Montclair Drive sidewalk constructionProject: Sidewalks will be constructed in spots where there are no pedestrian sidewalks along the eastern side from Hall-Johnson Road to Glade Road. Drainage structures, grading and restoration of landscaping will also be completed.