The city project will construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared-use path on the north side of Williams Drive, a new waterline, and street lighting from DB Wood Road to Jim Hogg Road and Serenada Drive to I-35.
- Update: The project’s design is complete, and officials anticipate it to go out to bid in late April.
- Timeline: 2023-27
- Cost: $18.6 million
- Funding sources: city of Georgetown, traffic impact fees, federal grants, tax increment financing
2. SE Inner LoopA 2.91-mile stretch of SE Inner Loop will be widened to a four-lane, divided road from Hwy. 29 to FM 1460. A shared-use path for pedestrians and bicycles will be added on one side.
- Update: The city is in the process of acquiring the right-of-way needed for the project. Design is complete and officials anticipate it to go out to bid in July.
- Timeline: 2022-28
- Cost: $70.6 million
- Funding sources: city of Georgetown, Georgetown Transportation Enhancement Corporation
3. Hwy. 29 WestThe Texas Department of Transportation will construct additional travel lanes, lengthen turn lanes and improve traffic signals on Hwy. 29 from Wolf Ranch Parkway to I-35 as well as add shared-use paths.
- Update: TxDOT is expected to begin construction in September.
- Timeline: 2023-27
- Cost: $12.31 million
- Funding source: Georgetown Transportation Enhancement Corporation
4. Austin Avenue pedestrian bridgesThis project will include construction of two pedestrian and bicycle bridges crossing the San Gabriel River, east of the existing Austin Avenue vehicular bridges.
- Update: The revised design is tentatively scheduled to be complete in July 2027.
- Timeline: 2023-TBD
- Cost: $21 million
- Funding sources: city of Georgetown, developer fees
5. Shell Road