The Hwy. 29 Bypass from RM 1869 to CR 279 in Liberty Hill is nearing completion, Daigh said.
- Timeline: anticipated completion late 2025
- Cost: $14.4 million
Ronald Reagan Boulevard provides north to south connection through unincorporated areas of Georgetown. Construction crews have started pouring bridge slabs for the boulevard’s widening from Hwy. 29 to FM 3405, Daigh said.
- Timeline: anticipated completion summer 2027
- Cost: $52.5 million
Precinct 3Crews are repaving and widening a portion of Sam Bass Road stretching from RM 1431 to Wyoming Springs Drive near Round Rock, according to the county’s website.
- Timeline: anticipated completion fall 2025
- Cost: $34.5 million
Officials broke ground on a 3-mile expansion to CR 255 near Georgetown on Feb. 28, Community Impact previously reported. The project is funded through Williamson County’s Road and Bridge fund, according to Daigh’s presentation.
- Timeline: anticipated completion summer 2026
- Cost: $20.8 million
An extension to Wyoming Springs from the intersection of Brightwater Boulevard and Creek Bend Boulevard to Sam Bass Road is also underway. Williamson County is partnering with the city of Round Rock, who is managing construction, per the presentation.
- Timeline: anticipated completion late 2026
- Cost: $25.9 million
Precinct 4Through a city of Round Rock partnership, construction is underway on an eastern extension of Old Settlers Boulevard from the intersection of North Red Bud Lane and CR 122 to CR 110, according to Daigh’s presentation.
- Timeline: anticipated completion fall 2025
- Cost: $14.9 million
Officials are widening a segment of CR 112 from the intersection of FM 1460 and AW Grimes to CR 117 through another partnership with the city of Round Rock, Daigh said.
- Timeline: anticipated completion late 2026
- Cost: $13.1 million
A separate CR 112 widening project with Round Rock is also underway. Construction will begin at CR 117 and extend to CR 110, per the presentation.
- Timeline: anticipated completion late 2026
- Cost: $20.4 million
Segment 2 of the East Wilco Highway from CR 137 to CR 404 broke ground in fall 2024, Community Impact previously reported.
- Timeline: anticipated completion summer 2028
- Cost: $64.2 million
No active projects are under construction in Precinct 1, but Daigh said there are “lots” of projects under design.