Georgetown City Council approved a construction contract with Ward & Burke Tunneling Inc. for a nearly $62 million Berry Creek Interceptor project at a Jan. 23 meeting.
The details
The Berry Creek interceptor—a sewer that transmits large volumes of wastewater to a wastewater treatment facility or sewer overflow—project consists of installing approximately 24,000 feet of wastewater pipe ranging in size from 8 inches to 60 inches via open cut and trenchless micro-tunneling, according to city documents.
The project also includes the installation of 46 polymer concrete manholes as well as ancillary items for completing the wastewater interceptor from Airport Road near Berry Creek Drive east to Pecan Branch Wastewater Treatment Plant, according to city documents.