Planning for a roughly 3-mile light rail extension to Austin-Bergstrom International Airport could take up to a year. (Rendering courtesy of Austin Transit Partnership)
East Austin's transportation projects range from a $344 million airport utility overhaul and new shared-use paths on Airport Boulevard to early planning for a light rail to Austin-Bergstrom International Airport.
Ongoing projects
Airport Boulevard shared-use path
Project: 10-foot-wide shared-use paths along the west side of Airport Boulevard from US 183 to Lamar Boulevard, with driveway consolidation, new curb ramps and a replacement MoKan Trail bridge.
Update: Paths are complete from North Lamar Boulevard to 46th Street. In East Austin, the stretch from MLK Jr. Boulevard to Springdale Road is under construction and should be finished by the end of January, according to Austin Transportation and Public Works. The section from 46th Street to MLK is on hold during I-35 construction, and work from Springdale Road to US 183 is expected to start in mid-2028.
Shared-use paths are complete along Airport Boulevard from North Lamar Boulevard to 46th Street.(Courtesy city of Austin)
Austin-Bergstrom International Airport: utility upgrades
Project: Upgrades to stormwater drainage, chilled and hot water piping, power distribution, telecommunications and reclaimed water lines across the airport campus to support the new Arrivals and Departures Hall and Concourse B.
Update: The airport broke ground on the project Oct. 19. The project now totals $344 million, up from a $120 million construction estimate. The Federal Aviation Administration has committed more than $16 million so far.
Project: A roughly 3-mile, mostly elevated extension from the planned Yellow Jacket station on East Riverside Drive to Austin-Bergstrom International Airport, following US 183 and Hwy. 71.
Update: The Austin Transit Partnership announced Nov. 10 that it had begun planning the extension, which ATP dropped from its scaled-down 2023 plan. Planning will take up to a year. Mayor Kirk Watson hopes to fit the extension into the existing light rail budget. Light rail's first phase, which runs east on Riverside Drive to Yellow Jacket Lane, is set to break ground in 2027.
Timeline: construction TBD
Cost: TBD
Funding source: TBD; federal funds are among options
Project: A center-running transit lane on Dean Keeton Street through the rebuilt I-35 frontage road intersection, part of TxDOT's I-35 Capital Express Central project.
Update: City Council committed $1 million Nov. 5. A city-state agreement on design and construction will follow. The lane is meant for buses such as CapMetro Rapid 837, which runs from the Expo Center Park & Ride through Mueller and UT to downtown.
A center transit lane planned for Dean Keeton Street at I-35 would serve buses such as CapMetro Rapid 837, which connects East Austin’s Expo Center to downtown.(Ben Thompson/Community Impact)
E. 51st Street Mobility Project
Project: Improvements to East 51st Street from I-35 to Berkman Drive, including reconstruction from Cameron Road to Berkman Drive with landscaped medians, protected bike lanes, tree-lined sidewalks and new crossings at Mueller Boulevard, Lancaster Court and Berkman Drive.
Update: Final design is expected this fall. Construction is now expected to start in fall 2027 and last 12-18 months, according to an Oct. 13 city presentation.