Austin is paying $2 million to renovate the site of a planned homeless services hub off I-35, after the city acquired the property for more than $4 million a year ago.
The big picture
The South Austin Housing Navigation Center is being developed to offer housing assistance and other services to the city's homeless population. That facility at 2401 I-35 is expected to replace the existing Sunrise Homeless Navigation Center south of Hwy. 290—which has proven controversial in its South Austin community and drawn legal and legislative scrutiny in recent years.
Austin pursued the new I-35 navigation center as a "purpose-built" space under city ownership and oversight, Homeless Strategy Officer David Gray previously said, rather than the current iteration operating out of Sunrise Community Church. City officials authorized the purchase of the I-35 property last fall for $4.38 million, ahead of an anticipated spring 2026 opening.
The navigation center has yet to launch, and the city is now targeting next summer. Sunrise was previously announced as the new facility's anticipated operator, and officials recently agreed to a $250,000 contract amendment with the nonprofit for outreach and services around the center before it opens. In response to community concerns, the city also convened a public advisory board for the center.
As those processes play out, an additional $2 million for facility renovations was authorized Nov. 19. That new funding will address issues like the navigation center's lack of functional air conditioning and Americans with Disabilities Act compliance, according to the city, along with other improvements.
Zooming in
While the $2 million for facility rehabilitations comes a year after the city acquired the facility, the city said some HVAC and ADA deficiencies were identified during its initial site evaluations and appraisals last year. However, limited initial findings were followed by further review that prompted the work now moving forward.
"The specific scope and severity of required improvements were further refined during facility walkthroughs conducted by [Austin Facilities Management, or AFM] project managers and subsequently validated through assessments performed by the design team," a city spokesperson said.
To date, the city has already completed several updates to prepare the site for future use, including landscaping, gate and fencing installations, removal of graffiti and an old sign pole, plumbing repairs, and asbestos abatement. Some older HVAC equipment has since been removed and additional ADA assessments were completed.
In addition to the air conditioning and accessibility projects, the newly authorized $2 million will also cover electrical upgrades, lighting and solar panel additions, roof sealing and other work.
"Planned site improvements at this point are to create an accessible pedestrian route to the entrance of the building from the sidewalk on the frontage road. In addition, we are sealing and re-striping the parking lot, removing diseased trees, improved security with a rear iron fence and drive gate," the spokesperson said.
The city's initial due diligence ahead of the 2025 property acquisition followed standard processes, with support from in-house and third-party specialists. Various assessments complied with city, state and federal requirements and best practices, according to the city. Still, some key reviews couldn't be completed until after the property came under Austin's ownership.
"It is important to note that until a facility is fully owned by the City, there are limitations on how in-depth inspections and evaluations can be. For example, we cannot remove drywall to expose interior utilities to fully understand their current condition during the due diligence phase," the spokesperson said.
The $2 million for renovations was added to the city's Capital Improvement Program as part of AFM's portfolio of planned civic projects. The work was assigned to Balfour Beatty Construction Group under Austin's job order program—a previously authorized pool of contractors rather than a new solicitation—that allows for a more flexible and efficient approach, according to the city.
"As building maintenance, repair, alteration, renovation or remediation work is needed, a work assignment is offered to contractors in the order of scoring rank. Balfour Beatty was the next contractor in the work rotation when this project was authorized," the spokesperson said.
What's next?
Sunrise and the city are moving ahead on further amendments to their agreement for outreach work related to the new navigation center this fall. Balfour Beatty is expected to begin work on the I-35 property in early 2027.
Originally slated for a vote this July, Sunrise's new contract for South Austin Housing Navigation Center operations is now expected to go before City Council in the second quarter of 2027. It will incorporate a "Good Neighbor Policy" from Austin Homeless Strategies and Operations, or HSO. After Sunrise moves into the renovated property, it's expected to open for homeless services by next August.
"We established quarterly benchmarks given the number of improvements, operational considerations, and City departments involved. Several components are moving forward simultaneously and require coordination across departments. However, the City Manager firmly established August 2027 as the deadline for opening the Housing Navigation Center," the spokesperson said. "HSO staff will continue working closely with AFM to monitor the renovation schedule and address any issues that could affect the timeline. We will also maintain regular meetings with the South Austin Housing Navigation Center Advisory Body to gather community input and inform our ongoing discussions with Sunrise regarding facility operations."