4 Lewisville, Flower Mound and Highland Village transportation updates

Morriss Road is currently undergoing panel replacement work.

Morriss Road is currently undergoing panel replacement work.

Image description
LFH-2019-06-7-1
Image description
LFH-2019-06-7-2
Image description
LFH-2019-06-7-3
Image description
LFH-2019-06-7-4

Morriss Road improvements


To allow for panel replacement work, portions of Morriss Road were reduced to one lane May 15. The lane reductions begin on the northbound lanes north of Tournament Drive and follow the panel replacements as they progress. Work on the 20-inch water line replacement from Forest Vista Drive to Garden Road was scheduled to begin May 28. The project includes concrete panel replacements from FM 3040 to Firewheel, Americans with Disabilities Act improvements from FM 3040 to Firewheel as well as 20- and 24-inch water line replacements from Forest Vista to Garden. Additional work includes FM 3040 and Morriss intersection improvements and a southbound left-turn lane extension at Morriss and Forest Vista.


Timeline: May 2019-2020
Cost: $5 million
Funding source: town of Flower Mound



Main Street reconstruction


The contractor is still working on curbs, sidewalks, driveways and crosswalks along the south side of Main Street east of Mill Street in Lewisville as well as installing electrical conduit for lighting. This will continue for the next 4-6 weeks. Once the south side of the street is substantially complete, the contractor will begin working on the north side of Main. The project is still on track to have Main substantially complete by September. The contractor will not work on Mill until Main is substantially complete. The project includes adding on-street parking; bicycle lanes; wider sidewalks, traffic signal modifications, and amenities such as benches and recycle bins on Main and Mill.


Timeline: January-September 2019
Cost: $8.5 million (Main and Mill cost)
Funding source: city of Lewisville



Highland Village bond projects


Highland Village City Council in May approved a $523,000 bid to Pavecon Public Works LP for the first phase of the 2017 street bond program. The construction project includes the reconstruction of seven streets. Those streets are Rosedale Street, Shasta Court, Ranier Court, Snowdon Court, Sheldon Court, Sugarloaf Court and Catesby Place. The street improvements earmarked for bond money include the reconstruction of 23 residential streets that were identified as failing or at the end of their life cycle. The streets will be reconstructed in four phases.


Timeline: mid-June-November 2019
Cost: $523,000
Funding source: city of Highland Village



Fairway Drive update


Fairway Drive across Grapevine Lake dam has been closed since August due to a slide at the dam. The Army Corps of Engineers is in the process of repairing the slide and had intended to close the road during the construction phase only. However, in January the Corps said the road will be closed indefinitely. The Corps said in order to reopen the road to the public, the embankment restoration project of the dam, repair of asphalt and the guardrail in the vicinity of the slide repair, and maintenance of the road—including crack sealing—must be complete, Flower Mound officials said in May. No date or schedule for reopening of the road was provided.

SHARE THIS STORY


MOST RECENT

Patients need blood every two seconds somewhere in the U.S., Hale said, and Type O is the most in-demand, according to the American Red Cross. (Courtesy Sanford Myers and American Red Cross)
American Red Cross sees urgent need for blood donations

The American Red Cross urgently needs blood donors of all types, according to Jan Hale with the organization's biomedical services department.

The Lewisville Adoption Center and the city of Lewisville will host their annual Paws in the Park event March 28. (Courtesy Lewisville Adoption Center)
Here's 10 things to do in March and April in Lewisville, Flower Mound and Highland Village

From basketball games to easter egg hunts, here are 10 upcoming events.

(Courtesy Adobe Stock)
Improvements to Yucca Drive and Churchill Drive in Flower Mound near completion

Construction crews are nearing completion on the Yucca Drive and Churchill Drive improvements project in Flower Mound. 

Denton County Commissioners Court meetings are held Tuesdays at 9 a.m. at 110 W. Hickory St., Denton. (Anna Herod/Community Impact Newspaper)
Denton County to apply for drug court grant

Denton County will submit an application to Texas Gov. Greg Abbott’s office for a $71,833 grant, which would benefit the Denton County Drug Court Program.

The Garden Ridge Trail is expected to be completed by the end of April. (Photo courtesy city of Lewisville)
Lewisville's Garden Ridge Trail expected to be completed in April

Although the city originally estimated that the project would be completed in February, officials say the project is now on track to be finished in April due to weather delays.

Makers on Main of Lewisville will relocate in March. (Photo courtesy Makers on Main)
Makers on Main of Lewisville to relocate in March

The gift and crafting boutique is set to relocate in March.

SignatureCare Emergency Center opened Feb. 19 in Lewisville. (Brian Pardue/Community Impact Newspaper)
SignatureCare Emergency Center now open in Lewisville

The emergency center, which is staffed with board certified physicians, will be open 24/7 year-round.

Lewisville City Council approved a special use permit Feb. 17 for a hotel planned for Rockbrook Drive. (Anna Herod/Community Impact Newspaper)
Lewisville City Council approves special use permit for hotel planned for Rockbrook Drive

Lewisville City Council unanimously approved a special use permit which will allow Nortex Hotel Group to build a 125-room, four-story hotel on Rockbrook Drive off of SH 121.

Early voting for the March 3 primary elections begins Feb. 18 for Denton County voters.
Denton County 2020 Primary Election Guide

Early voting for the March 3 primary elections begins Feb. 18 for Denton County voters.

Green Truck Cafe opened Feb. 11 in Lewisville. (Courtesy Green Truck Cafe)
Green Truck Cafe opens in Lewisville

The cafe serves a variety of handcrafted coffee and espresso drinks as well as breakfast and lunch.

(Courtesy ReClaim Construction)
ReClaim Construction now open in Lewisville

The business, which was previously located in Frisco, offers general contractor services.

Back to top