Arizona Drive street maintenance
The project: Arizona Drive construction is part of a greater downtown redevelopment project. Work will include reconstructing the roads from Ash Street to Cedar Street.
The update: A $3.12 million contract was approved for the project during an April 9 Celina City Council meeting.
- Timeline: 300 days starting on a TBD date
- Cost: $3.12 million shared for both streets
- Funding source: city of Celina
The project: Colorado Drive construction is part of a greater downtown redevelopment project.
The update: A $3.12 million contract was approved for the project during an April 9 Celina City Council meeting.
- Timeline: 300 days starting on a TBD date
- Cost: $3.12 million shared for both streets
- Funding source: city of Celina
The project: This is the third phase of lighting installation for Preston Road.
The update: The project is on track to finish by the beginning of the summer, according to the city’s capital improvement projects dashboard.
- Timeline: summer 2023-late spring 2024
- Cost: estimated at $1.57 million
- Funding source: city of Celina
The project: Bothwell Boulevard, which is located inside the Sutton Fields development, has regular residential lighting on the sides but not arterial lighting, according to an April 9 Celina City Council presentation. Adding lighting to the median would take 75 days and includes installing light poles, luminaries, conduits and meters along the road.
The update: Celina City Council members chose to table a contract for the street construction after debating whether the city should be responsible for the project during an April 9 meeting. An update on the project is expected at a future meeting.
- Timeline: TBD
- Cost: $1.09 million
- Funding source: TBD