First Street traffic signal addition
The project: This project includes bringing two new traffic signals expected to help when a new high school is built in the area, according to Prosper’s capital improvement projects dashboard. The signals will be located at the First Street and Artesia Boulevard intersection.
Update: Construction will also include intersection improvements, such as pedestrian ramps and straight sidewalks. This project is in its design phase with construction tentatively slated to start in summer 2025.
- Timeline: summer 2025-TBD
- Cost: estimated at $525,000
- Funding source: town of Prosper
The project: This road project will include constructing a modified three-lane commercial couplet from Preston Road to First Street, a modified collector street from First Street to Broadway Avenue, and a rural neighborhood street from Broadway to Fifth. Construction will include paving and drainage work, according to Prosper’s capital improvement projects dashboard.
Update: This project is in its design phase with construction tentatively scheduled to start in spring 2024.
- Timeline: spring 2024-spring 2025
- Cost: estimated at $4.79 million
- Funding source: town of Prosper
The project: Tackling Teel Parkway, this project will bring two lanes on the east side of an ultimately six-lane divided roadway between US 380 and First Street, according to the town’s capital improvement projects dashboard.
Update: Construction, which is slated to begin in 2024, will include adding a concrete roadway with curb and gutter, underground drainage improvements, and median landscaping improvements.
- Timeline: early spring 2024-fall 2025
- Cost: estimated at $9.5 million
- Funding source: town of Prosper