Check out five campuses set to open for the 2025-26 school year in Prosper ISD and Celina ISD.

Prosper ISD

1. Jana Thomson Elementary School

Project: This is a new elementary school, which will be Prosper ISD’s 19th on the district west side.

Update: Driveways have been poured along with parking lots and all grade beams have been completed on the project, according to an August district construction update. The Prosper ISD board of trustees voted to name the campus for former district educator and school board member Jana Thomson in June.
  • Location: Located in the Legacy Gardens neighborhood
  • Timeline: opening for the 2025-26 school year
2. Virgie Witt Smothermon Elementary School


Project: This will be Prosper ISD’s 20th elementary school.

Update: The school construction is underway. Grade beams have been completed in three areas, according to an August district construction update.
  • Location: Located on the corner of Lamplighter Drive and Sunrise Lane
  • Timeline: opening for the 2025-26 school year
3. Pete Moseley Middle School

Project: This will be Prosper ISD’s sixth middle school that will open on the west side of the district.

Update: Exterior metal wall panel installation is ongoing and the placing of all rooftop HVAC units is complete, according to an August district construction update.
  • Location: Located on the corner of Parvin Parkway and Elder Road
  • Timeline: opening for the 2025-25 school year
4. Richland High School


Project: This will be Prosper ISD’s fourth high school on the west side of the district.

Update: Internal and external work is still underway including athletic facilities tied with the campus.
  • Location: 3080 Fishtrap Road, Prosper
  • Timeline: opening for the 2025-26 school year
Celina ISD

5. Elementary School No. 5

Project: This will be Celina ISD’s fifth elementary school.


Update: Earlier this year, the district’s board of trustees approved a $42.45 million maximum price for the campus, which is currently under construction.
  • Location: 1105 Big Bend Lane, Celina
  • Timeline: Opening for the 2025-26 school year
  • Capacity: 750