1. Windcrest Drive repairs
Crews are making road and sidewalk repairs on Windcrest Drive between Spring Creek Parkway and Tennyson Parkway. One lane is scheduled to remain closed to traffic at all times.
Timeline: early March-August
Cost: $400,000
Funding source: city of Plano
2. Parker Road intersection improvements
A project to improve intersections of Parker Road with Alma Drive and Coit Road will widen the road, improve signals and realign intersections. Crews have yet to start due to franchise utility relocation efforts but will begin at (A) Coit Road and will move to (B) Alma Drive following completion.
Timeline: December 2020-February 2023
Cost: $2.1 million
Funding sources: city of Plano, Collin County
3. Park Boulevard repairs
Crews will be making pavement and sidewalk repairs on Park Boulevard from Los Rios Boulevard to Shiloh Road/East Spring Creek Parkway. One lane is scheduled to remain closed to traffic at all times.
Timeline: April-August
Cost: $300,000
Funding source: city of Plano
4. Park Boulevard intersection improvements
A project to improve five Park Boulevard intersections, including at (A) Coit Road, (B) Custer Road, (C) Alma Drive, (D) K Avenue and (E) Jupiter Road, will widen the roads and realign intersections. Crews have completed work at the Coit and Jupiter intersections and plan to next make improvements at Custer. Work has begun on the signal improvements at the Alma location, and paving improvements will follow after the Custer Road location is complete.
Timeline: October 2020-November 2022
Cost: $4.2 million
Funding sources: city of Plano, Collin County
5. Coit Road widening
A project that will widen Coit Road between Mapleshade Lane and the President George Bush Turnpike includes updates to pedestrian facilities and signal improvements as well as construction of additional turn lanes.
Timeline: June 2021-August 2022
Cost: $2.1 million
Funding sources: city of Plano, Collin County
6. Plano Parkway and Coit Road ultrathin overlays
Crews will be placing an ultrathin overlay on the section of (A) Plano Parkway from Preston Road to Park Boulevard in late August and September. From September-October, an ultrathin overlay will also be placed on (B) Coit Road from Parker Road to SH 121. One lane will remain closed at all times at both worksites, with an additional lane closed from 9 p.m.-6 a.m. Mondays-Saturdays.
Timeline: August-October
Cost: $4.6 million
Funding source: city of Plano