Intersection pavement, median and traffic signal improvements
Four intersections across Plano will be receiving improvements, with construction starting this month. The intersections of McDermott Road and Coit Road, Legacy Drive and Hedgcoxe Road, West Spring Creek Parkway and Windhaven Parkway, and Jupiter Road and Los Rios Boulevard will all be included in the project. The intersections will be getting additional westbound and eastbound lanes, traffic signal updates, new pavement markings and pedestrian crossing updates.
- Timeline: August 2023-May 2024
- Cost: $2.8 million
- Funding source: city of Plano bond
This project is modifying the signals, removing road humps, maximizing left-turn lane lengths and adding right-turn lanes on Park Boulevard from Coit Road to Jupiter Road. Dual left-turn lanes were installed at Alma Drive, Coit Road, Custer Road and Jupiter Road. Only improvements at the intersection of Park Boulevard and K Avenue are yet to be completed. The completion date was postponed from July to September.
- Timeline: October 2020-September 2023
- Cost: $4.2 million
- Funding sources: city of Plano, Regional Toll Revenue, Collin County
Crews are making improvements to the intersections of A Parker Road and Coit Road, and B Parker Road and Alma Drive. The project includes the widening of street pavement, improvements to pedestrian ramps and traffic signal modifications. The Coit Road intersection will have double left-turn lanes added on Parker Road, and the Alma Drive intersection will have a right-turn lane added on both roads. The completion date was postponed from January to May of next year.
- Timeline: July 2023-May 2024
- Cost: $2.9 million
- Funding sources: city of Plano, Regional Toll Revenue, Collin County
Crews will be making pavement and sidewalk repairs on Independence Parkway from Spring Creek Parkway to SH 121 in both directions. One lane will remain closed to traffic at all times, with a second lane to be closed daily between 9 a.m. and 4 p.m.
- Timeline: September 2023-September 2025
- Cost: $8.92 million
- Funding source: city of Plano
Crews will be making pavement and sidewalk repairs on Midway Road from Park Boulevard to Spring Creek Parkway in both directions. One lane will remain closed to traffic at all times, with a second lane to be closed daily between 9 a.m. and 4 p.m.
- Timeline: September 2023-December 2024
- Cost: $2.73 million
- Funding source: city of Plano