Construction in May will include continued paving of the new northbound lanes north of FM 546. A new southbound right turn lane will also be constructed at Industrial Boulevard. Through August, the northbound lane of Airport Drive will be closed at Harry McKillop with a temporary detour through Wattley Way.
Project cost: $1.7M
Estimated timeframe: April 2020 – April 2021
Funding source(s): city of McKinney, Roadway Impact Fee