See how work is progressing on these developments underway in the McKinney area.

1. Independent Financial second building

Exterior site work and building core and shell work is wrapping up on Independent Financial’s second headquarters building. The project is located on a 10-acre site at SH 121 and Grand Ranch Parkway. Landscaping is in progress and will be completed before tenants move in.

Space: 198,000 square feet

Timeline: January 2021-June 2022


2. Kaizen office tower

Crews are continuing to work on the exterior facade of the building, which includes installing the glass and architectural metal panels on the exterior. The project is located at the northeast corner of SH 121 and Alma Road. In the coming weeks, work will begin on the interior finishes of the project. During the summer, crews will direct their attention to landscaping and interior finish out.

Space: 200,000 square feet

Timeline: May 2021-September 2022


3. Tupps Brewery expansion

Following the groundbreaking, construction permits have been issued and crews are mobilized on the site of the new Tupps Brewery building, located across from the McKinney Flour Mill on East Louisiana Street. In early May, crews poured the foundation for the brewery building, which is now being erected. The existing building that will house the taproom will be disassembled and reconfigured for heating and air conditioning.

Space: 45,000 square feet

Timeline: January-late 2022