Wendy's: 10921 Virginia Parkway, McKinney
Type of work: new construction
Timeline: Feb. 21-May 29
Estimated cost: $700,000
McKinney Economic Development Corporation: 7300 SH 121, Ste. 200, McKinney
Type of work: renovation/alteration
Timeline: Feb. 1-Aug. 31
Estimated cost: $900,000
United Pacific: 3701 N. Macdonald St., McKinney
Type of work: new construction
Timeline: Sept. 15-Dec. 15
Estimated cost: approximately $1.6 million
Walgreens: 8996 Stacy Road, McKinney
Type of work: renovation/alteration
Timeline: May 9-Aug. 23
Estimated cost: $625,000
Basepoint-McKinney: 4733 Medical Center Drive
Type of work: additions to existing building
Timeline: Jan. 1-April 30
Estimated cost: $1.2 million