Construction crews are nearing completion on the Yucca Drive and Churchill Drive improvements project in Flower Mound.

The project includes the reconstruction of Yucca from Sagebrush to about 700 feet south of Cross Timbers Road and extending Churchill approximately 400 feet to connect to Yucca.

It also consists of sidewalk and trail improvements. Paving along Yucca is complete, but crews are still doing sidewalk work on the west side of the street.

Timeline: August 2018-March 2020

Cost: $2.3 million


Funding source: town of Flower Mound