Ongoing Projects
1. Ray White Road widening
Project: Construction of a four-lane divided road with 5- to 8-foot sidewalks on both sides of the road, street lights, storm drain improvements and modifications to the roundabout at Ray White Road and Park Vista Boulevard.
Update: The westbound leg of the roundabout and the intersection of Wall Keller Price Road and Ray White Road will be closed until Aug. 28.
- Timeline: Expected completion summer 2027
- Cost: $22 million
- Funding source: city of Fort Worth
Project: Repair damage below the Bear Creek Parkway bridge, east of the road's intersection with Lakeridge Drive
Update: The neighborhood trail will close during construction.
- Timeline: Expected completion in September
- Cost: $530,300
- Funding source: TBD
Project: Reconstructing and repaving all of Chandler Road
Update: Lane closures are expected to occur during construction.
- Timeline: Expected completion by the end of September
- Cost: $685,566
- Funding source: TBD
Project: A new traffic signal will be installed at North Beach Street and Champion View Parkway along with accessible ramps, pedestrian sidewalks and crosswalks and accessible pedestrian signals.
Update: Temporary top signs have been added at the intersection.
- Timeline: Expected completion in February 2026
- Cost: $2 million
- Funding source: city of Fort Worth
5. Mount Gilead Road Trail expansion
Project: A hike and bike trail will be added to the current trail along Mount Gilead Road from Woodborough Lane to Roanoke Road. The 10-foot wide trail will extend 1,350 feet to the east and 500 feet to the south of the established trail.
Update: Minimal traffic impact is expected.
- Timeline: August 2025-May 2026
- Cost: About $567,000
- Funding source: city of Keller
Project: The work on Cannon Parkway will include 6-foot reinforced concrete pavement, 6-inch curbs and 18-inch gutters from Byron Nelson Boulevard to Holley Parkway. The work along Litsey Road includes 8-inch reinforced concrete pavement, 6-foot curbs and 18-foot gutters from Byron Nelson Boulevard to Independence Parkway.
Update: Construction is expected to begin July 16 with Cannon Parkway from Holey Parkway to Byron Nelson Boulevard. Construction will occur in sections.
- Timeline: Not available
- Cost: $176,000
- Funding source: city of Roanoke