Construction began Feb. 7 to add a new fiber optic network through OneSource Communications in Trophy Club. The first phase of the five-phase plan will have service online in late March or early April. The other four phases are expected to be complete by late spring. Construction is being done from 8 a.m. to 7 p.m. on weekdays, and the city expects the disruptions to be minimal.

Timeline: February-late spring

Cost: private funding

Funding source: OneSource Communications