Curious about upcoming renovations, businesses and attractions in Keller, Roanoke and northeast Fort Worth? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

CoCo Shrimp: 1301 Keller Parkway Unit 100, Keller

Type of work: New Construction

Timeline: Jan. 15, 2023-April 15, 2023

Estimated cost: $240,000


First Baptist Church of Keller: 225 Keller Parkway, Keller

Type of work: New Construction

Timeline: Feb. 1, 2023-Aug. 1, 2023

Estimated cost: $3 million


Little Lilly Sushi: 1004 Keller Parkway, Unit 106, Keller

Type of work: Renovation/Alteration

Timeline: Jan. 15, 2023-March 15, 2023

Estimated cost: $95,000


MIla & Rose: 620 Henrietta Creek, Roanoke

Type of work: New Construction

Timeline: Jan. 16, 2023-Oct. 31, 2023

Estimated cost: $2.6 million


South West Data Center: 931 Litsey Road, Roanoke

Type of work: Renovation/Alteration

Timeline: March 1, 2023-Dec. 1, 2023

Estimated cost: $500,000