Want to read the latest development news in Keller, Roanoke, and Northlake? Find details on the five latest commercial projects filed in your community below. The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.

OutPost 36 BBQ: 1801 S. Main St., Keller

Type of work: Additions to Existing Building

Timeline: Oct. 30, 2022-May 1, 2023

Estimated cost: $800,000




Alliance Gateway 57: 1051 Republic Drive, Roanoke

Type of work: Renovation/Alteration

Timeline: Jan. 3, 2023-March 1, 2023

Estimated cost: $450,000




Carhartt: 16101 Wolf Crossing, Northlake

Type of work: Renovation/Alteration

Timeline: Nov. 14, 2022-April 29, 2023

Estimated cost: $1,371,136




Doctors Urgent Care: 1234 FM 407, Suite 200, Northlake

Type of work: New Construction

Timeline: Nov. 29, 2022-Feb. 27, 2023

Estimated cost: $261,303




Bombay Vapor: 5000 TX-114, Unit 110, Northlake

Type of work: Renovation/Alteration

Timeline: Jan. 2, 2023-March 3, 2023

Estimated cost: $120,000