August Development highlights


Developers are turning dirt throughout Grapevine, Collevyille and Southlake. Some projects are for office or hospitality use, and some are large community recreational projects. The following are development highlights of different commercial and recreational projects that are under construction.


1. Ground is expected to break on a Stand Rock Hospitality project in 2018.  The $330 million project will feature guest suites, indoor and outdoor water amenities, a 20,000-square-foot family entertainment center and timeshare hotel condominium units. The water park and resort will be located on the Palmeiro Tract, a 185-acre tract of land located north of Grapevine Mills in Grapevine. The project will be built in two phases. Phase 1 is expected to take around 15 months to complete.


2. A Perry’s Steakhouse & Grill is under construction at 2400 W. SH 114, Grapevine. The restaurant is expected to open in the fall. The restaurant will have seating for a total of 449 people—365 interior seats and 84 patio seats. The family-owned and -operated restaurant’s menu items include filet mignon, prime rib eye, grilled salmon, pecan-crusted gulf red snapper and steamed lobster tail as well as soups and salads. Dessert items include creme brulee, rocky road bread pudding, bananas Foster, and a milk chocolate peanut butter candy bar.


3. The new Grapevine Public Safety Building is set to be officially open in September. The building, located at 1007 Ira E. Woods Ave., Grapevine, will house the police department, municipal court, fire department administration, information technology department and logistics. This multilevel facility will feature three different buildings on one campus totaling approximately 104,000 square feet. A ribbon cutting is set for Sept. 5 at 10:30 a.m.


4. Southlake’s second Class A office building, The Offices at Kimball Park, broke ground in July 2016. The building, located at the northwest corner of SH 114 and Kimball Avenue, received a temporary certificate of occupancy in early August. Tenants Keller Williams Realty DFW Southlake and Liberty Mutual moved into the building in early August as well. The four-story building’s tenants include Executive Medicine, Independence Title, Medici Development Partners, Liberty Mutual and Keller Williams Realty DFW Southlake so far.


5. A 253-room Westin Southlake will break ground in early 2018. Construction is slated to take 18-20 months. The hotel will be located on 6.83 acres at 1200 SH 114. When complete, the four-star hospitality building will be a conference center and full-service hotel. Amenities include a restaurant that serves breakfast, lunch and dinner; in-room service; a pool; a fitness center; and boutique retail spaces.


6. On June 21 the city of Colleyville purchased 0.987 acres between Casa Lane and Terra Cotta Way for $800,000. City staff said purchasing the land allows the city to have a role in the future of the space right next to Colleyville City Hall and the Colleyville Public Library. Currently the property is being used to host and enhance the city’s special events, including the recent Summer Reading Grand Finale. The city does have the ability to exercise the property for an economic development purpose.