Ongoing projects
1. Panther Creek Parkway construction
Project: Panther Creek Parkway will be created into a six-lane divided highway spanning Dallas North Tollway to Preston Road.
Update: The project is under construction, according to the city's capital improvement website.
- Timeline: March 2024-December 2025
- Cost: $56.4 million
- Funding sources: Collin County, city of Frisco
Project: The project will construct a four-lane divided roadway from Panther Creek Parkway to PGA Parkway.
Update: The project is under construction and moves toward completion next year.
- Timeline: March 2024-June 2025
- Cost: $5.99 million
- Funding source: city of Frisco
Project: The project will create a new two-lane roadway from Dallas Parkway to Panther Creek Parkway in anticipation of the new Universal Kids Resort, which is expected to open in 2026.
Update: The project is under construction and moves toward its completion later this year.
- Timeline: September 2023-December 2024
- Cost: $12.94 million
- Funding source: city of Frisco
Upcoming projects
4. Custer Road light installation
Project: The intersection at Custer Road and Gartner Road will see a new traffic light installed.
Update: The project is in the design phase. The design phase was expected to end at the end of quarter two. Construction is projected to be complete at the end of the year.
- Timeline: TBD-December 2024
- Cost: $250,000
- Funding source: city of Frisco
Project: The project will span along Teel Parkway from Stafford Middle School to Olive Branch Drive. The project will widen the road from two lanes to four lanes, according to Frisco’s capital improvement database.
Update: The project is in its planning phase.
- Timeline: September 2025-December 2026
- Cost: $10 million
- Funding source: city of Frisco
Project: A new traffic signal will be added to the intersection at Coit Road and Charismatic Parkway, according to the city’s capital improvement website.
Update: The project is in the design phase. The project was supposed to start construction at the end of June.
- Timeline: TBD-December 2024
- Cost: $250,000
- Funding source: city of Frisco
Project: A new traffic signal light will be added to the intersection at Main Street and Kings Ridge Road.
Update: The project is in the design phase, and it should be completed by the end of this year, according to the city’s capital improvement website.
- Timeline: TBD-December 2024
- Cost: $250,000
- Funding source: city of Frisco
Project: Several roundabouts will be added to Frisco Street at Technology Drive, Sports Village Road, All Stars Avenue and Research Drive.
Update: The project is still in its design phase with construction to start later this year.
- Timeline: December 2024-March 2026
- Cost: $9 million
- Funding source: city of Frisco
Project: The project will reconstruct Meadow Hill Drive from North County Road to Rogers Road.
Update: The project has been placed on hold.
- Timeline: TBD
- Cost: $3.7 million
- Funding source: city of Frisco
Project: The project will construct a four-lane divided roadway along Frisco Street from Cobb Hill Drive to Panther Creek Parkway.
Update: The project has been placed on hold, according to the city’s capital improvement website.
- Timeline: TBD
- Cost: $8.71 million
- Funding source: city of Frisco