1. Hwy. 290 Project E
Construction on the direct connector between Hwy. 6 northbound and Hwy 290 eastbound in Houston is ongoing. The first overpass bridge structure was completed, and major utility relocations were wrapped up in June. Crews are now working on westbound frontage roads between FM 1960 and Huffmeister Road.
Timeline: July 2015-late 2017 Cost: $135.4 million Funding sources: Texas Department of Transportation
2. Louetta Road extension
Harris County is working to extend Louetta Road as a four-lane concrete boulevard from Blanco Trails Lane to Telge Road in Cypress. The project was published for bidding April 26.
Timeline: summer 2016-TBD Cost: $2.3 million Funding sources: Harris County Precinct 4