A number of construction projects and road improvements are nearing completion in the Conroe and Montgomery area.
This list is not comprehensive.
Upcoming projects
1. Calvary Road widening


Local · Trusted · Free
The Morning Impact — your neighborhood's most important stories, delivered every morning.


A number of construction projects and road improvements are nearing completion in the Conroe and Montgomery area.
This list is not comprehensive.
Upcoming projects
1. Calvary Road widening
Project: Calvary Road will be reconstructed to be a four-lane asphalt road between Lake Conroe Bay Road and I-45.
Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
Timeline: TBD
Cost: $1.01 million
Funding source: Montgomery County road bond funds
Ongoing projects
2. I-45 direct connector
Project: A direct connector is being constructed to connect northbound I-45 with eastbound Hwy. 242.
Update: According to a Sept. 4 media update from the Texas Department of Transportation, the project completion has dropped from 20% to 10% complete.
Timeline: second quarter 2025-third quarter 2028
Cost: $42.63 million
Funding sources: federal, state funds
3. Hwy. 105 widening segment 1
Project: Between 10th Street and South Loop 336, Hwy. 105 is being widened from two to four lanes.
Update: Per TxDOT’s Sept. 4 media update, this project is 65% completed.
Timeline: March 2023-second quarter 2028
Cost: $52.65 million
Funding source: state funds
4. Hwy. 105 widening segment 2
Project: Between South Loop 336 and FM 1484, Hwy. 105 is being widened from two to four lanes.
Update: Per TxDOT’s Sept. 4 media update, this project is 98% completed.
Timeline: February 2023-third quarter 2026
Cost: $52.65 million
Funding source: state funds
5. South Loop 336 widening
Project: South Loop 336 is being widened from two to four lanes between I-45 and Ladera Creek Trace.
Update: This project is 80% completed, according to TxDOT’s Sept. 4 media update.
Timeline: November 2024-third quarter 2027
Cost: $20.57 million
Funding source: state funds
6. FM 1097 widening
Project: From Blueberry Hills Road to Lake Conroe Hills Drive, FM 1097 is being widened from two to four lanes.
Update: This project is 96% completed, according to TxDOT’s Sept. 4 media update.
Timeline: second quarter 2022-third quarter 2026
Cost: $20.21 million
Funding sources: federal, state funds
7. FM 1097 at Atkins Creek project
Project: This project at FM 1097 and Atkins Creek includes culvert replacement and shoulder additions.
Update: According to TxDOT’s Sept. 4 media update, this project is 95% completed.
Timeline: third quarter 2025-third quarter 2026
Cost: $4.41 million
Funding sources: federal, state funds