Construction on the $259 million 183A Toll Phase 3 project located north of Leander was about 40% completed as of December, said Mike Sexton, acting director of engineering at the Central Texas Regional Mobility Authority.
Structural and concrete work, such as retaining walls and bridges, are being built, and in 2023, work on Hwy. 29 to build a 30-foot-deep underpass will begin.
Drivers will begin to see the effects of this construction on Hwy. 29 in early 2023, and it will continue for about a year until work on the highways is completed, Sexton said.
Once completed, the 6.6-mile extension from Hero Way to Hwy. 29 will consist of two tolled lanes in each direction located mainly within the existing US 183 median. The project will also include shared-use paths, according to CTRMA documents.