The Bell Boulevard realignment project in Cedar Park, which will relocate the stretch of Bell Boulevard between Buttercup Creek Boulevard and Cedar Park Drive to the alignment of Old Highway 183, is going to require a substantial utility relocation, according to the city.
Overhead utilities will be relocated outside of the new roadway alignment and placed underground—a project that could cost nearly $4 million, according to city documents.
Cedar Park City Council voted unanimously during a Nov. 14 meeting to authorize an agreement for the construction of the utility relocation project with Austin Underground Inc. in an amount not to exceed $3,906,205.
The city underwent a competitive sealed proposal process to determine the right firm to complete the project. The city determined Austin Underground Inc. offered the best value, though the company’s initial proposed cost was over budget. Since the project is of an uncommon sort, typical costs were difficult to estimate, according to the city. The city met with Pedernales Electric Cooperative to explore ways to bring the project within budget.