In an effort to ease transportation surrounding the semiconductor manufacturing site in Taylor, officials from Williamson County, the Texas Department of Transportation and Samsung Austin Semiconductor will hold a ribbon-cutting ceremony celebrating the completion of the Samsung Highway on June 7.
The specifics
The event will mark the completion of several road projects in southwest Taylor. These include the reconstruction and expansion of CR 401, improvements to CR 404 and FM 973, water realignment on CR 404, and the completion of segments 1 and 2 of the Samsung Highway, according to a county news release.
The Samsung Highway project involves the construction of a four-lane roadway adjacent to the ongoing Samsung plant. Additionally, the new roadway connects FM 3349 and FM 973 in an effort to lessen curves on CR 404, according to previous reporting by Community Impact, which will increase safety around the forthcoming semiconductor facility.