The Harris County Flood Control District has been given the go-ahead for construction of three connected stormwater detention basins located along Braeswood Boulevard at the I-610 Loop.
Work could begin within a few days and will take about four months to complete, the Harris County Flood Control District said.
“We are working with a sense of urgency to break ground and complete hundreds of individual flood control projects like these across Harris County,” Harris County Judge Lina Hidalgo said in a release.
The basins, located between Endicott Lane and South Post Oak Road, will primarily collect stormwater from area streets and control runoff into Brays Bayou, said Gary Zika, a project manager for the flood district.