Over 14 months after voters approved a $480 million road bond package for Montgomery County and the first batch of funds was made available to commissioners, the Precinct 2 Commissioner’s Office has nearly completed all of its bond projects.
Twelve of the 19 road projects involving widening and restructuring roadways have been completed, per a status update from Commissioner Charlie Riley’s office. Of the remaining projects, five are under active construction and two are waiting to begin construction.
The big picture
Precinct 2 was awarded $120 million from the 2025 bond to complete the projects. Staff said the ability to move quickly on so many of the projects came from staying in active communication with potential contractors as soon as funds were available for projects to begin work.
“Commissioner Riley notified the contractors to let them schedule their job options as soon as the funds were allocated,” staff said.
Of the projects under construction, some are expected to be complete by the end of the year, including Roberts Cemetery Road. The roadway is receiving the final layer of asphalt and restriping in November before being completed.
Since funding for the bond projects is authorized in a series of bond sales, the commissioner’s office said they also work with state and local resources in order to share costs where possible.
The goal of the projects in part is to address increasing traffic patterns along many corridors. Some roads, for example, have seen an increase of more than 30% in traffic dating back to 2021, according to data from the Texas Department of Transportation.
Despite progress being made on the projects, it comes as Montgomery County is issuing smaller amounts of funding in hopes that interest rates in the coming months will settle down, said John Robuck, who is consulting the county on investments and is part of BOK Financial Services.
Questions about those interest rates stem in part from ongoing national issues, he said.
All of the bond projects aim to address rehabilitating and widening roadways that have received significant use. According to average daily traffic data from TxDOT, major roadways like Hardin Store Road have seen steady use as population growth continues in the area.
Kuykendahl Road, which connects the Magnolia area to The Woodlands, is also being widened to accommodate increased traffic at the intersection of FM 1488 and for an intermediate school.
Something to note
Robuck said the October round of bond sales is the smallest the county will make since interest rates have climbed higher than were projected.
As of October, municipal interest rates are at 5.21%, notably higher than the historical average of 4.07% since 2001.
Commissioners agreed to authorize the sale of $35 million in bond funds to provide enough money for road projects through June with the hope that interest rates will settle down by then, Robuck said. The county currently has $57 million in the bank for road bond projects, not including the $35 million in bond funds.
“National debt, the Iran conflict and inflationary fears have pushed interest rates up a lot higher than we projected," Robuck said.
Stay tuned
Precinct 2 staff said the next projects the office will be focusing on include the Magnolia Relief Route, Woodtrace Boulevard expansion and extending FM 149 to Hwy. 249.
However, funding the projects will require additional partnerships and time in order to begin, officials involved in the series of projects said. Riley’s office said they seek the public’s patience as work continues and as funding is secured for additional projects.
“Thank you for your patience,” the commissioner’s office said in a statement. “Thank you for your vote of confidence to generate the funding for all these road improvements. The results for bringing all these projects to a close will be to provide safer, long-lasting roads built to withstand the impact of daily vehicle traffic.”