Following an update on Old Stagecoach Road and Center Street, projects included in the 2022 Kyle Road Bond, the Kyle City Council provided direction that will result in longer travel times during construction but allow the project to be completed faster.

The Old Stagecoach Road project will reconstruct and widen a 2.2-mile section of roadway into a four-lane minor arterial from FM 2770 to Veterans Drive. The Center Street project includes improvements to Jack C. Hays Trail from Veterans Drive to north of Witte Road. It will also expand Center Street from Veterans Drive to Main Street in downtown Kyle, increasing it from two to three lanes, according to the Kyle Road Bond website.



The overview

City Council was presented with two construction options:
  1. Bid projects independently as designs are completed to expedite delivery.
  2. Delay bidding on some segments until others are finished to minimize traffic impacts during construction.
Council ultimately chose the first option, prioritizing a faster completion timeline despite an estimated 23% increase in travel time during construction. With this approach, the Old Stagecoach Road and Center Street projects are expected to be completed by Q3 2027, according to the city presentation.


The rejected second option would have extended the project's completion to Q3 2028, increasing the construction timeline and potential travel impacts by 15 months. It also would have resulted in an estimated $770,000 in additional costs due to inflation but would have limited the travel time increase to 17%.

Estimated travel time impacts, according to the presentation, were calculated using the worst-case construction scenario for each alternative, predicting travel times for each direction and segment.

The background

In November 2022, Kyle voters approved Proposition A, a road bond funding eight transportation projects across the city, totaling 10.3 miles of new roads, reconstructions, and widening projects to improve Kyle’s transportation network.


What's next

The timeline for the option chosen is as follows: