The Texas Department of Transportation is performing construction work on existing and new exit and entrance ramps to and from I-35 between the Blanco River in San Marcos and FM 150 in Kyle.

The construction will force the closures of some lanes on I-35 throughout the night and into the early morning next week.

In Hays County:

June 19-20


Angel Brothers, the project contractor, will close the outside lane of the northbound I-35 main lanes between the Blanco River and Yarrington Road to complete striping and move signs to the new exit ramp north of the Blanco River. Once completed, the new Exit 210 to Yarrington will be opened permanently to traffic. The existing exit ramp to Yarrington, 0.4 miles south of Yarrington, will be permanently closed and removed.

The I-35 outside lane closure is scheduled from 9 p.m. on June 19 to 5 a.m. on June 20. The inside and middle lane of traffic on I-35 will be open to allow traffic to pass during this lane closure.

June 20-21


Angel Brothers will close the outside two lanes of the northbound I-35 main lanes from 0.5 miles south of Yarrington to 0.6 miles north of Yarrington to move portable concrete traffic barriers from one ramp to another ramp under construction.

The I-35 outside lane closure is scheduled to begin at 9 p.m. on June 20, and the middle lane closure will begin at 11 p.m. on June 20.  All lane closures associated with this portion of the project will last until 5 a.m. on June 21.  The inside lane of traffic on I-35 will be open to allow traffic to pass during this lane closure; however drivers should anticipate delays through this area overnight.

June 21-22


Angel Brothers will close the outside lane of the northbound I-35 main lanes from 0.5 miles south of Yarrington to 0.6 miles north of Yarrington to complete striping and move signs to the new exit ramp north of Yarrington. Once completed, the new Exit 213 to FM 150 (Center Street) will be opened permanently to traffic. The existing Exit 213, 0.83 miles south of FM 150, will be permanently closed and removed.

The I-35 outside lane closure is scheduled from 9 p.m. on June 21 to 5 a.m. on June 22.  The inside and middle lane of traffic on I-35 will be open to allow traffic to pass during this lane closure.

June 22-23


Angel Brothers will close the outside lane of the northbound I-35 main lanes from 0.5 miles south of FM 150 to 0.1 miles north of FM 150 to complete striping and move signs to the new entrance ramp. Once completed, the new entrance ramp to I-35, 0.5 miles south of FM 150, will be opened permanently to traffic.

The I-35 outside lane closure is scheduled from 9 p.m. on June 22 to 5 a.m. on June 23.  The inside and middle lane of traffic on I-35 will be open to allow traffic to pass during this lane closure.