Adidas: 3939 I-35 S., Ste. 583, San Marcos
Type of work: renovation/alteration
Estimated cost: $900,000
Timeline: Sept. 20-Dec. 22
Scope of work: new Adidas location; demolition of interior space to shell condition; new partitions, finishes and fixtures
Armani Exchange Outlet: 3939 I-35 S., Ste. 325, San Marcos
Type of work: renovation/alteration
Estimated cost: $360,000
Timeline: July 1-Sept. 30
Scope of work: interior renovations to existing Mercantile Occupancy tenant space
San Marcos High School: 2601 Rattler Road, Ste. 100, San Marcos
Type of work: renovation/alteration
Estimated cost: $56,000
Timeline: June 1-Aug. 31
Scope of work: minor revisions to the existing credit union to create a private office and to create secure lobby access from the school side of the facility
Medina Building: 202 Pleasant St., San Marcos
Type of work: renovation/alteration
Estimated cost: $450,000
Timeline: July 15, 2022-Jan. 15, 2023
Scope of work: 2,400-square-foot renovation
Tint World: 118 Trademark Drive, Ste. 502, Buda
Type of work: renovation/alteration
Estimated cost: $150,000
Timeline: Aug. 1-Oct. 1
Scope of work: interior tenant improvement for an auto tint shop
Four Hands Buda Building 2: Fire Cracker Drive, Buda
Type of work: renovation/alteration
Estimated cost: $1.3 million
Timeline: July 1, 2022-Feb. 1, 2023
Scope of work: first-generation interior finish-out to provide offices, restrooms and support areas within an existing one-story warehouse building; affects walls, doors and mechanical, electrical and plumbing systems
Cap Aviation: 1629 Robert S. Light Blvd., Bldg. 2, Buda
Type of work: renovation/alteration
Estimated cost: $220,000
Timeline: May 27-Nov. 1
Scope of work: new office space within the existing warehouse
Nitro Swimming: 3425 S. FM 1626, Kyle
Type of work: new construction
Estimated cost: $7,500,000
Timeline: Aug. 1, 2022-Oct. 1, 2023
Scope of work: new construction of indoor swimming facility to include training pool, lesson pool, changing spaces and indoor restrooms
Freebirds: 19220 I-35, Ste. 101, Kyle
Type of work: new construction
Estimated cost: $350,000
Timeline: Sept. 1-Dec. 20
Scope of work: interior finish-out of an existing shell building to accommodate a Freebirds restaurant
Smokey Mo’s BBQ: FM 1626, Kyle.
Type of work: new construction
Estimated cost: $650,000
Timeline: July 5-Oct. 5
Scope of work: upfit of a new, unoccupied tenant space; new barbecue restaurant with seating for 52 guests; additional 46 seats on an exterior, covered patio.