With one project complete, Buda continues to provide updates on its 2014 bond package

Buda City Council voted to send two applications for the 2018-2019 Platinum Planning Program Project Call.

Buda City Council voted to send two applications for the 2018-2019 Platinum Planning Program Project Call.

During the November 2014 election, Buda voters approved five bond packages equaling up to $55 million. On Dec. 12, the city of Buda sent out updates for the 2014 bond package. As of December 2017, all projects are in progress except for Proposition 2, the construction of the new public safety building for the Buda Police Department, which is complete.

Proposition 1 – Municipal Complex


The proposition 1 bond funded the construction of the future municipal complex that will house the new city hall, public library and the Buda Economic Development Corporation.

Construction Timeline: Feb. 2017-April 2018
Cost: $24.9 million
Status: Final touches are in the works. As of Dec. 5., the pedestrian bridge, parking lot, interior and exterior trim, millwork, landscaping and the last 5 percent of the glass and glazing work need to be completed.

Proposition 2 – Public Safety Building


The proposition 2 bond funded the construction of the 14,420 square-foot building that is now the new home of the Buda Police Department. The building features a gated enclosure for office parking and has two exit routes leading to Main Street. The building also houses a community meeting room for public meetings and interdepartmental training.

Construction Timeline: Jan. 2017-Nov. 2017
Cost: $6.75 million
Status: Complete

Proposition 3 – Streets


Proposition 3 focused on four on Buda's most problematic roads to improve traffic flow, pedestrian walkways and road safety.

Construction Timeline:
Old Goforth Road: Feb 2017-Oct. 2018
San Antonio Street: Feb. 2017-May 2018
Main Street at RM 967 intersection: Feb. 2017-Oct. 2018
Main Street from Bradfield to Railroad Street: Feb. 2017-Nov. 2018

Cost: $12.25 million

Status
Old Goforth Road: The project design is 95 percent complete. Negotiation of utility relocation agreement with Goforth Special Utility District and Guadalupe-Blanco River Authority for joint bid of utility work and roadway construction is almost done. However, letting was delayed due to Pedernales Electric Cooperative relocating due to recovery efforts for Hurricane Harvey and Irma.

San Antonio Street: The project design is 95 percent complete. Discussion is still occurring with city staff on the project. The project is currently delayed to create a more cohesive result.

Main Street at RM 967 intersection: The project design is 95 percent complete. Discussion is still occurring with city staff on the project. Because a TxDOT Advanced Funding Agreement is required, changes in TxDOT's processes and a project backlog has resulted in delays.

Main Street from Bradfield to Railroad Street: The project design is 90 percent complete. Construction on Main Street projects will start after major work activities and delivery of large and heavy items have occurred to prevent damage to the new roadway.

Proposition 4 – Drainage


Six projects were selected by the Buda Bond Advisory Committee to be included in the 2014 Drainage Plan. After the drainage projects are complete, the city should see a reduction of residential and commercial flooding and water elections rising over roadways in Buda.

Construction Timeline: Jan. 2017-Nov. 2017
Bluff Street Area, Buda Fire Station Area and West Goforth Road Area (project 1): June 2018-June 2019

Houston Street Area (project 2): Feb. 2017-Nov. 2018

Oxbow Neighborhood Area (project 3): March-Dec. 2018

Lifschutz Headwaters Area (project 4): N/A

Cost: $7 million

Status
Bluff Street Area, Buda Fire Station Area and West Goforth Road Area (project 1): The project design is 60 percent complete, and utility coordination has started.

Houston Street Area (project 2): Invitations for bids are under final review. Two easements acquisitions are on progress, and utility coordination is ongoing.

Oxbow Neighborhood Area (project 3): Invitations for bids draft is under review. 17 proposed easements acquisitions are on progress, and utility coordination is in progress.

Lifschutz Headwaters Area (project 4): The administrative process has been started.

Proposition 5 – Parks and Trails


Construction Timeline: Feb. 2018-Nov. 2017
Cost: $8 million
Status: Construction documents need to be drafted along with sending out an invitation for bids before starting construction.
By Starlight Williams
Starlight Williams joined Community Impact Newspaper July 2017 after graduating Loyola University New Orleans. She spent her time covering city government, education and business news in the Buda and Kyle area. Starlight moved on from Community Impact July 2018.


MOST RECENT

Residents will be able to comment on projects funded through the CDBG-CV grant at a June 2 City Council meeting. (Anna Herod/ Community Impact Newspaper)
City of San Marcos seeks public input on projects for COVID-19 response funds

A virtual public hearing will take place at a June 2 San Marcos City Council meeting to comment on proposed programs and projects to be added to the 2019-20 Community Development Block Grant Action Plan using CDBG-Coronavirus Response funds.

texas-reopening
LIST: What is open, closed in Texas and how businesses can operate

Texas openings are staggered with different opening dates and operating limits.

All patients, residents and staff at Texas' 23 state hospitals and supported living centers are to be tested for coronavirus. (Courtesy Adobe Stock)
Texas to test all state hospitals, supported living centers for COVID-19

All patients, residents and staff at Texas' 23 state hospitals and supported living centers will be tested for coronavirus regardless of symptoms or exposure.

Hays County Judge Ruben Becerra is encouraging testing for residents. (Joe Warner/Community Impact Newspaper)
MAY 23 ROUNDUP: Top stories from this week in Central Texas

Read the most popular stories from the past week of Community Impact Newspaper's coverage of Central Texas.

In a letter addressed to state agencies and higher education institutions, Gov. Greg Abbott, Lt. Gov. Dan Patrick and House Speaker Dennis Bonnen said the reduced budget comes in preparation to the coronavirus pandemic’s impact on state finances expected to be felt in the coming months. (Courtesy Fotolia)
Budget cuts slated for Texas state agencies, higher education institutions in 2020-21 biennium

Texas state agencies and institutions of higher education to expect a 5% reduction in budget plans for the 2020-21 biennium as part of the state's response to the economic ramifications of the ongoing coronavirus pandemic.

Gov. Greg Abbott is waiving the late fee for Texas Alcoholic Beverage Commission license and permit renewals that have lapsed since March 13, according to a May 20. (Courtesy Adobe Stock)
Gov. Abbott removes late-fee barrier for Texas Alcoholic Beverage Commission license, permit renewal

Gov. Greg Abbott is allowing the Texas Alcoholic Beverage Commission to waive the late fee for license and permit renewals that have lapsed since March 13, according to a May 20 press release.

Here are the coronavirus updates to know in Hays County. (Community Impact staff)
746 coronavirus tests have been reported in Hays County in 2 days, yielding 20 new cases

22% of all coronavirus cases recorded since March have been reported in the last 2 days

San Marcos continues to add residents at a steady pace. (John Cox/Community Impact Newspaper)
DATA: Population growth for San Marcos mirrors Hays County increase since 2010 census

San Marcos has seen a 44% population increase, while Hays County has gained 47% since 2010.

Pinstack opening during coronavirus
As entertainment centers across Austin reopen with bowling and more, the future of arcades remains murky

Concurrent with the governor’s Phase 2 rules, several Austin-area entertainment centers will reopen in the coming days and weeks with bowling, axe throwing, karaoke and laser tag.

 Texas State University announced that Sewell Park will remain closed until July 6. (John Cox/ Community Impact Newspaper)
Sewell Park in San Marcos remains closed until July 6

Texas State University announced May 21 that Sewell Park will remain closed until July 6 citing coronavirus concerns.

Buda's population has grown 132% since 2010, according to census numbers. (John Cox/Community Impact Newspaper)
NEW: Buda population has made 132% jump since 2010 census

All of Hays County sees steady growth in new numbers released by U.S. Census Bureau.