Update: The southbound side of the roadway is complete, and the traffic switch is in place.
- Timeline: completion scheduled for fall 2026
- Cost: $54.5 million
- Funding sources: developer contributions, type B sales tax revenue, certificate of obligation bonds, Williamson County contributions
Red Bud Lane North wideningProject:
The project includes upgrading an existing two-lane road to a four-lane divided roadway with intersection and pedestrian improvements.
Update: All work on the northbound lanes is expected to be completed by the end of summer, with construction on southbound lanes to begin soon.
- Timeline: completion scheduled spring 2027
- Cost: $34.7 million
- Funding sources: developer contributions, type B sales tax revenue, certificate of obligation bonds
Old Settlers ExtensionProject:
A new four-lane divided segment of Old Settlers Boulevard will be built, including a bridge, connecting North Red Bud Lane to County Road 110.