The city of Round Rock has several transportation projects in various stages of construction.
Upcoming projects
Kenney Fort Boulevard extension segments 5 and 6
Project: The project will extend Kenney Fort Boulevard to University Boulevard from its current terminus at East Old Settlers Boulevard.
Update: Round Rock City Council approved the purchase of 1.5 acres of land using eminent domain in November. The project is currently under design.
• Timeline: construction timeline not yet available
• Cost: $493,841 (land purchases), full cost not yet available
• Funding source: Type B sales tax revenue
CR 118 reconstruction
Project: CR 118 will be reconstructed as a three-lane rural section with a center turn lane.
Update: Round Rock City Council approved the purchase of just under one acre for wastewater and temporary construction easements in November using eminent domain. The project is currently under design.
Timeline: construction timeline not yet available
Cost: $583,393 (land purchases), full cost not yet available
Funding source: Type B sales tax revenue
Old Settlers Bridge rehabilitation
Project: Crews will address failing concrete in the bridge’s approach at the intersection of East Old Settlers Boulevard and A.W. Grimes Boulevard.
Update: Round Rock City Council awarded a construction contract to Taylor Bridge in November.
Ongoing projects
Greenlawn Boulevard widening
Project: The city is reconstructing the road from four lanes to six lanes with pedestrian and lighting improvements. Design for the project now includes a traffic signal and a turn lane near the IDEA Public Schools campus.
Update: Round Rock City Council updated the scope of construction to include traffic signal equipment, electrical work, pavement markings, and additional paving materials and concrete in November, adding $367,950 to the project cost.
McNeil Road railroad culverts
Project: This project adds and enlarges drainage facilities and culverts along McNeil Road and the Union Pacific Railroad line near downtown Round Rock.
Update: Park Lane is closed to traffic for several weeks in November to facilitate work on the project.
Completed projects
South Chisholm Trail Road reconstruction
Project: The city reconstructed Chisholm Trail Road from Sam Bass Road to RM 620, with drainage, pedestrian and lighting improvements.
Update: The road opened to traffic in early November, with striping expected to be complete by the end of the month.